Required Pre-Establishment & Pre-Operation Clearances

Pre-Establishment Clearances

Clearance Type Name of Clearances Department Checklist Procedure Timeline
Pre-Establishment Clearances Change of Land Use Revenue Visit Link Visit Link 60 Days
(Please see Page No. 11 to 16 for checklist and procedure)
Consent To Establish (under Water & Air Act) Pollution Control Committee Visit Link Visit Link 90 Days
(Please select Forms & Notification menu from Top left to know the checklist)
Provisional NOC from Fire Department Fire Visit Link Visit Link 30 Days
Electricity Connection Electricity Visit Link PDF 15 Days
(Checklist is avialable in wizard)
Water Connection or Certificate of Non-Availability of Water Public Works Department Visit Link 07 Days
Registration under Shops and Establishment Act Labour Visit Link Visit Link 20 Days
Registration under Weights & Measure Weights & Measure Visit Link 30 Days
(Please see Page No. 11 of above Citizen Charter)
Registration under the Building and Other Construction Workers Labour Visit Link Visit Link 20 Days

Pre-Operation Clearances

Clearance Type Name of Clearances Department Checklist Procedure Timeline
Pre-Operation Clearances Consent to Operate (under Water & Air Act) Pollution Control Committee Visit Link Visit Link 90 Days
Authorization under Hazardous Waste Rules Pollution Control Committee Visit Link Visit Link 90 Days
Factories License Chief Inspector for Factories & Boiler Visit Link Visit Link 20 Days
Registration Certificate of Establishment Inter State Migrant Workmen (RE&CS) Act, 1979 Labour Visit Link Visit Link 20 Days
Registration under Boiler Act Chief Inspector for Factories & Boiler Visit Link Visit Link 60 Days
(ie. Application on company letter head, Plans of Pipeline and Fees as per schedule)
Final NOC from Fire Department Fire Visit Link Visit Link 28 Days
NOTE: There is no other license/NOC/approval required in the UT other than the ones listed on above in respect of business related clearances.